Land cable connection Submarine cable connection Strategic partner Establish and strengthen partnerships/connectivity
Data Center Location
NTP campus, on part of lot PTD 5224, Nusajaya, Johor, Malaysia
Building information
Tier Lv:T3+ Floor area:38,500 m2 Number of floors: 2 above-ground two-story buildings Load bearing: 15 kN/m2
Design Parameter
External: Dual 60MW (33kV) IT power: 21.6~24MW Single cabinet density: 8~25kW/ cabinet, customizable Power architecture: DR 3+1 Customizable Refrigeration system: Precision air conditioning and water-cooled chiller, can be customized
Malaysia – JHB2
Hyperscale Data Centers Continue To Be Intensively Cultivated
Release of AIGC Data center full stack solution – Intelligent Power Module 3.0 – magnetic suspension phase change cooling system – Integrated modular solution
Data Center Location
39KM from PTP port It is 42KM from downtown Sinsan 28KM
from Senai International Airport 60KM
Building information
Mains input: 2N Firewood configuration: N+1 Construction area: 22500 ㎡ Number of floors: 3 Building mode: Steel structure Water/diesel backup time 12/12 hours Designed average annual PUE ≈1.33
Design Parameter
IT Capacity: 26.6MW Single cabinet power: 21kW Cooling system: maglev phase change + backplane wind wall IT UPS redundancy configuration: DR/2N
Indonesia-JKT1
Advanced Data Center
Metta DC’s Jakarta data center is a state-of-the-art, 35MW facility located in the Jababeka Industrial Estate, West Java, featuring six data halls and 10,000 sqm of white space, capable of housing up to 3,000 racks
Data Center Location
Bekasi Area (Outer Jakarta) – Jababeka Industrial
Building Facility
• 3 Storey building • 10,000 sqm total IT Hall • Building seismic damper (until 9RS)
Data Hall
• 500 racks per data hall • Average rack density 5 kW • Maximum high density 15kW • Rack dimension: 48U, 600mmx1200mm
Mechanical & Electrical
• N+1 Generators Configuration • N+1 Power Distribution • N+1 UPS configurations
Case1
Phase 1: Delivering 132MW
IT Load: 351MW, DC Capacity: 800MW (2* 400MW, 2N Configuration)
Timeline:
Case2
MEP Delivery: 4-6 months per building with 35MW capacity
IT Load: 320MW, DC Capacity: 600MW (3* 200MW, DR Configuration)